PROJECT DESCRIPTION STATUS CLIENT GAD
101 Steel design of dog legged ramp on single column for Jhansi Completed 2017 Rail Vikas Nigam Ltd. (RVNL)
102 Steel design of 36m clear span Foot Over Bridge (FOB) for 7 stations Completed 2019 Rail Vikas Nigam Ltd. (RVNL)
[Contractor: Galvano India Pvt. Ltd.]
103 School Building at Jhansi With Plan Area 4000 m^2 Completed 2019 Rail Vikas Nigam Ltd (RVNL)
104 Steel design of Foot Over Bridge (FOB) over 4 spans (Total Length 104m) at Mirzapur Railway station Completed 2019 Contractor: Galvano India Pvt. Ltd.
[North Central Railways]
105 Steel Design of FOB over 3 spans (Total Length 94m) at Chowki railway station, near Allahabad Completed 2019 Contractor: Es. Pee. Enterprises
[North Central Railways]
106 Steel Design of Shed (21mx60m) with Gantry Girder of 20Ton capacity at Allahabad On Going Es Pee Enterprises  
107 Steel Design of FOB over 2 spans (Total Length 34m) at ATTA railway station, near Jhansi On Going Rail Vikas Nigam Ltd (RVNL)
[contractor: Galvano India Pvt. Ltd.]